Drainage Renewal and Traffic Diversion Coordination

This Can Tho drainage-renewal case covers wet-season pipe installation, traffic diversion, temporary drainage and coordination with neighbouring businesses.

Pre-construction surveys

Survey pipes, manholes, road levels and flood points together. Mark uncertain locations for investigation instead of relying solely on old drawings during excavation.

Implementation controls

  1. Provide temporary drainage routes and emergency pumping before closing the existing system.
  2. Excavate, install, inspect and backfill in short sections to limit open trenches.
  3. Update diversions as work moves, maintaining pedestrian and emergency access.
  4. Check pipe invert levels, joints and manholes before reinstating the road.

Continued monitoring

Rainfall observations and post-completion inspections help assess performance. Involve the maintenance team early and continue checking settlement, blockages and areas around manhole covers.